124. Not later than 120 days after having obtained the last authorization necessary or the favourable decision from the Régie de l’énergie, a person who wishes to obtain a pipeline construction or use authorization must apply to the Minister in writing.
O.C. 1253-2018, s. 124.
In force: 2018-09-20
124. Not later than 120 days after having obtained the last authorization necessary or the favourable decision from the Régie de l’énergie, a person who wishes to obtain a pipeline construction or use authorization must apply to the Minister in writing.